East River Esplanade Stabilization and Reconstruction Phase 2
-
90% complete
-
0% complete
-
0% complete
This project will stabilize and reconstruct portions of the East River Esplanade.
Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.
Project Timeline
Design
Start Date: February 2019
Projected Completion Date:
March 2020
Adjusted Completion Date:
April 2022
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
East River Esplanade
, Manhattan
East River Esplanade between East 96th Street and East 125th Street
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 05/24/2022