Highland Park Lower East Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    39% complete

This project will reconstruct the eastern half of the lower playground area, and performance area at Highland Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: June 2021

Construction

Start Date: June 2021
Projected Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $3,872,000
Funding Source: Mayoral

Location

Highland Park , Queens
Jamaica Avenue between Lynwood and Elton Streets

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/26/2021

Was this information helpful?