Citywide Pool Piping Hangers and Supports Reconstruction (CNYG-419M)

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the pool piping hangers and supports at various locations citywide.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: November 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Locations

  • Betsy Head Park , Brooklyn
    Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
  • Crotona Park , Bronx
    Fulton Avenue, Crotona Park North, South, East
  • Hamilton Fish Park , Manhattan
    Between East Houston & Stanton Streets
  • Jackie Robinson Park , Manhattan
    Bradhurst & Edgecombe Avenues, West 145 Street to West 155 Street
  • Lyons Pool , Staten Island
    Murray Hulbert Avenue between Victory Boulevard and Hannah Street
  • Red Hook Recreation Area , Brooklyn
    Otsego, Bay, Hicks, Lorraine, Court, Halleck Streets
  • Sunset Park , Brooklyn
    41 Street, 44 Street, between 5 Avenue and 7 Avenue
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/16/2018