Citywide Pool Piping Hangers and Supports Reconstruction (CNYG-419M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    54% complete

This project will reconstruct the pool piping hangers and supports at various locations citywide.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: November 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: December 2019

Construction

Start Date: January 2020
Projected Completion Date: January 2023

Understand how we build parks.

Funding

Total Funding: $1,396,000
Funding Source: Mayoral

Locations

  • Betsy Head Park , Brooklyn
    Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
  • Crotona Park , Bronx
    Fulton Avenue, Crotona Park North, South, East
  • Hamilton Fish Park , Manhattan
    Between East Houston & Stanton Streets
  • Jackie Robinson Park , Manhattan
    Bradhurst & Edgecombe Avenues, West 145 Street to West 155 Street
  • Lyons Pool , Staten Island
    Murray Hulbert Avenue between Victory Boulevard and Hannah Street
  • Red Hook Recreation Area , Brooklyn
    Otsego, Bay, Hicks, Lorraine, Court, Halleck Streets
  • Sunset Park , Brooklyn
    41 Street, 44 Street, between 5 Avenue and 7 Avenue
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/05/2020