Citywide Intermediate Pool Filter Plants Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct filter plants at various intermediate-sized pools citywide.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: February 2019
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020
Completion Date: June 2021

Construction

Start Date: September 2021
Projected Completion Date: September 2023

Understand how we build parks.

Funding

Total Funding: $393,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/25/2021

Was this information helpful?