Citywide Intermediate Pool Filter Plants Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct filter plants at various intermediate-sized pools citywide.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: February 2019
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020
Completion Date: June 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 08/03/2021

Was this information helpful?