Queens Community Boards 8-14 and Bronx Reforestation FY20

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees in the Bronx, and in Queens Community Boards 8-14.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: February 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Adjusted Completion Date: November 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Various locations in the Bronx and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020