Queens Community Boards 1-7 and Brooklyn Reforestation FY20

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees in Brooklyn, and Queens Community Boards 1-7.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: February 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: November 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Various locations in Brooklyn and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020