Monsignor Kett Playground Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Monsignor Kett Playground, including the court areas, play areas, and security and sports lighting.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: January 2019
Projected Completion Date: January 2020
Adjusted Completion Date: April 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Monsignor Kett Playground , Manhattan
West 204th Street between 10th Avenue and Nagle Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/21/2020