Astoria Pool Filtration System Reconstruction
-
50% complete
-
0% complete
-
0% complete
This project will reconstruct the filtration system at Astoria Pool.
Project Update: Parks is continuing to develop the documents to build this project and applying for necessary permits.
Project Timeline
Design
Start Date: September 2019
Projected Completion Date:
March 2021
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Astoria Park
, Queens
19th Street at 23rd Drive