Flushing Meadows Corona Park Electrical Vault Reconstruction (Hurricane Sandy)

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the electrical vault in Flushing Meadows Corona Park that was damaged by Hurricane Sandy.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: August 2019
Projected Completion Date: February 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Federal

Location

Flushing Meadows Corona Park , Queens
Grand Central Parkway, Whitestone Expressway between 111th Street and College Point Boulevard, Park Drive East

 