Brooklyn Street Tree Planting FY20 - Community Boards 6,7,10,12

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will plant new street trees in Community Boards 6, 7, 10, and 12 in Brooklyn.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Adjusted Completion Date: February 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020