Manhattan Street Tree Planting FY20 - Community Boards 1,3,5,6,8,11
-
100% complete
-
100% complete
-
55% complete
This project will plant new street trees in Community Boards 1, 3, 5, 6, 8, and 11 in Manhattan.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: September 2018
Projected Completion Date:
December 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
November 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2020
Adjusted Completion
Date:
January 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
- Private
Last updated: 02/26/2021