Manhattan Street Tree Planting FY20 - Community Boards 1,3,5,6,8,11

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    55% complete

This project will plant new street trees in Community Boards 1, 3, 5, 6, 8, and 11 in Manhattan.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: November 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020
Adjusted Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $4,500,000
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

Various locations in Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 12/01/2020