Manhattan Street Tree Planting FY20 - Community Boards 1,3,5,6,8,11

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    55% complete

This project will plant new street trees in Community Boards 1, 3, 5, 6, 8, and 11 in Manhattan.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: November 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $4,500,000
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

Various locations in Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 07/05/2020