Queens Street Tree Planting FY20 - Community Boards 7,8,11

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will plant new street trees in Community Boards 7, 8, and 11 in Queens.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: August 2021
Adjusted Completion Date: December 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project