Queens Street Tree Planting FY20 - Community Boards 9,10,14

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    98% complete

This project will plant new street trees in Community Boards 9, 10, and 14 in Queens.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: April 2020

Construction

Start Date: June 2020
Projected Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $2,875,000
Funding Source: Mayoral

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project

Last updated: 04/15/2021