Queens Street Tree Planting FY20 - Community Boards 9,10,14

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new street trees in Community Boards 9, 10, and 14 in Queens.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: April 2020

Construction

Start Date: June 2020
Projected Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $2,875,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020