Rainbow Playground Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the play and seating areas in Rainbow Playground, including the play equipment, safety surfacing, spray shower, fencing, benches, pavement, and drinking fountain.
Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.
Project Timeline
Design
Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
September 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Rainbow Playground
, Brooklyn
6th Avenue and 56th Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 02/26/2021