Fort Hamilton Park Sport Courts Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct basketball and tennis courts in Fort Hamilton Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

We are currently soliciting bids for this project. If you are interested in submitting a bid on this project, you can find the documents on our Bid Solicitations page.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: July 2020
Adjusted Completion Date: October 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Fort Hamilton Athletic Field , Brooklyn
83rd Street between Narrows Avenue and Colonial Road

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/22/2020