Osborn Playground Multi-Purpose Area Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the multi-purpose area at Osborn Playground.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: December 2018
Projected Completion Date: December 2019
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: September 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Osborn Playground , Brooklyn
Linden Boulevard between Osborn Street and Hegeman Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/22/2020