Sunners Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct Sunners Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: December 2018
Projected Completion Date: December 2019
Completion Date: August 2020

Procurement

Start Date: August 2020
Projected Completion Date: May 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Sunners Playground , Brooklyn
Kings Highway, Avenue H, East 49th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/19/2020