  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    39% complete

This project will reconstruct the playground area in Grace Playground, including the play equipment, safety surfacing, spray shower, fencing, and utilities.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: May 2020

Procurement

Start Date: May 2020
Projected Completion Date: February 2021
Completion Date: January 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023

Understand how we build parks.

Funding

Total Funding: $1,950,000
Funding Source: City Council

Location

Grace Playground , Brooklyn
Vermont Street between Pitkin Avenue and Belmont Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/30/2022

Was this information helpful?