Grace Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the playground area in Grace Playground, including the play equipment, safety surfacing, spray shower, fencing, and utilities.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: May 2020

Procurement

Start Date: May 2020
Projected Completion Date: February 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Grace Playground , Brooklyn
Vermont Street between Pitkin Avenue and Belmont Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/19/2020