Seton Falls Park Sidewalk and Fence Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the sidewalks and fencing at Seton Falls Park.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: February 2019
Projected Completion Date:
February 2020
Completion Date:
February 2020
Procurement
Start Date: February 2020
Projected Completion Date:
October 2020
Adjusted Completion
Date:
August 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Seton Falls Park
, Bronx
East 233rd Street between Baychester Avenue and Seton Avenue
Project Staff
Project Liaison: Michelle Martell