MacNeil Park Steps Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct the steps along the waterfront at MacNeil Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Borough President
  • City Council

Location

Hermon A. MacNeil Park , Queens
Poppenhusen Avenue between 115th Street and College Place

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 01/22/2020