Brookville Park Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the synthetic turf field at Brookville Park.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: December 2019

Procurement

Start Date: December 2019
Projected Completion Date: September 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Brookville Park , Queens
232nd Street between 144th Avenue and 145th Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 06/03/2020