Brookville Park Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf field at Brookville Park.

Project Timeline

Design

Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: December 2019

Procurement

Start Date: December 2019
Projected Completion Date: September 2020
Completion Date: December 2021

Construction

Start Date: January 2022
Projected Completion Date: January 2023
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $3,015,000
Funding Source: City Council

Location

Brookville Park , Queens
232nd Street between 144th Avenue and 145th Avenue

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 07/01/2022

Was this information helpful?