Springfield Park Basketball Courts and BBQ Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    9% complete

This project will reconstruct the basketball courts, and install new picnic tables, grills, charcoal bins, trees, and an accessible path to the BBQ area in Springfield Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2018
Projected Completion Date: February 2020
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: December 2020
Completion Date: April 2022

Construction

Start Date: July 2022
Projected Completion Date: July 2023

Understand how we build parks.

Funding

Total Funding: $3,300,000
Funding Sources:
  • City Council
  • Mayoral

Location

Springfield Park , Queens
Springfield Boulevard between 145th Road and 147th Avenue

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 10/04/2022