Roy Wilkins Park Black Spectrum Theatre Pathways and Lawn Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the pathways and lawn area adjacent to the Black Spectrum Theatre.
Project Update: A date has been set for construction to begin.
Project Timeline
Design
Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date:
June 2020
Procurement
Start Date: June 2020
Projected Completion Date:
March 2021
Completion
Date:
April 2022
Construction
Start Date: September 2022
Projected Completion Date:
June 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Roy Wilkins Recreation Center
, Queens
Baisley Boulevard at 177th Street
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 07/01/2022