Clove Lakes Park WWII Veterans War Memorial Ice Rink Condensers Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the rink condensers at the WWII Veterans War Memorial Ice Rink in Clove Lakes Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: August 2018
Projected Completion Date: December 2018
Completion Date: January 2019

Procurement

Start Date: January 2019
Projected Completion Date: October 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Clove Lakes Park , Staten Island
Victory Boulevard at Clove Road

 