Frederick Johnson Playground Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    29% complete

This project will reconstruct the play area at Frederick Johnson Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: February 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: November 2019
Completion Date: January 2020

Construction

Start Date: February 2020
Projected Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $5,740,000
Funding Source: Mayoral

Location

Frederick Johnson Playground , Manhattan
Adam Clayton Powell Jr. Boulevard (7th Avenue) between West 150th Street and West 151st Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/18/2020