Project Timeline
Design
Start Date: October 2017
Projected Completion Date:
February 2019
Completion Date:
March 2019
Procurement
Start Date: March 2019
Projected Completion Date:
November 2019
Completion
Date:
January 2020
Construction
Start Date: February 2020
Projected Completion Date:
July 2021