Harlem Lane Playground and Frederick Johnson Playground Sports Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Harlem Lane Playground, and it will demolish the existing comfort station and construct a new basketball court and synthetic turf field at Frederick Johnson Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: February 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: October 2022

Understand how we build parks.

Funding

Total Funding: $8,925,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 04/09/2021