Harlem Lane Playground and Frederick Johnson Playground Sports Courts Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct Harlem Lane Playground, and it will demolish the existing comfort station and construct a new basketball court and synthetic turf field at Frederick Johnson Playground.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: February 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • State

Locations

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 05/22/2019