Frederick Johnson Playground Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a new comfort station at Frederick Johnson Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: February 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: November 2019
Completion Date: February 2022

Construction

Start Date: June 2022
Projected Completion Date: December 2023

Understand how we build parks.

Funding

Total Funding: $4,699,000
Funding Source: Mayoral

Location

Frederick Johnson Playground , Manhattan
Adam Clayton Powell Jr. Boulevard (7th Avenue) at West 150th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/28/2022

Was this information helpful?