St. Michael's Playground Synthetic Turf Field Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the synthetic turf field at St. Michael's Playground.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date:
June 2021
Procurement
Start Date: June 2021
Projected Completion Date:
March 2022
Adjusted Completion
Date:
October 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
St. Michael's Playground
, Queens
30th Avenue, 31st Avenue, Brooklyn Queens Expressway, Boody Street
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project