Noble Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the play area at Noble Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Procurement

Start Date: February 2020
Projected Completion Date: November 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Noble Playground , Bronx
Noble Avenue, Bronx River Avenue, Bronx River Parkway, Cross Bronx Expressway

 

Project Staff

Project Liaison: Michelle Martell