Lincoln Terrace Park Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    27% complete

This project will reconstruct path pavements and seating areas in Lincoln Terrace Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: July 2020
Completion Date: January 2021

Construction

Start Date: February 2022
Projected Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: $4,000,000
Funding Source: Mayoral

Location

Lincoln Terrace / Arthur S. Somers Park , Brooklyn
Eastern Parkway, Rochester Avenue, East New York Avenue, Portal Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/28/2022