Lion's Pride Playground Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Lion's Pride Playground.

Project Update: The schematic design for this project has been approved. Parks is now developing construction documents for this project and applying for necessary permits.

Project Timeline

Design

Start Date: August 2018
Projected Completion Date: August 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council

Location

Lion's Pride Playground , Brooklyn
Van Sinderen Avenue, Riverdale Avenue, Snediker Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/19/2019