Cadman Plaza Park Oval Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the oval at Cadman Plaza Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: April 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Cadman Plaza Park , Brooklyn
Between Cadman Plaza East, Cadman Plaza West, the Brooklyn Bridge, and the Brooklyn War Memorial

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/27/2020