Yellowstone Park Fencing Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the fencing at Yellowstone Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: December 2019

Procurement

Start Date: December 2019
Projected Completion Date: September 2020
Adjusted Completion Date: June 2022

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Yellowstone Park , Queens
68th Avenue, 68th Road, 108th Street, Yellowstone Boulevard

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 05/17/2022

Was this information helpful?