Coney Island Boardwalk Security Measures Construction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct bollards and other security measures at entrances to Coney Island Boardwalk.

Project Update: Parks is continuing to develop the documents to build this project and applying for necessary permits.

Project Timeline

Design

Start Date: June 2019
Projected Completion Date: June 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Coney Island Beach & Boardwalk , Brooklyn
Brighton 15th Street to West 37th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/03/2020