Manhattan Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct synthetic turf fields at various locations in Manhattan.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: March 2019

Construction

Start Date: April 2019
Projected Completion Date: April 2020
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $4,037,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 12/13/2019