Manhattan Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    40% complete

This project will reconstruct synthetic turf fields at various locations in Manhattan.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: March 2019

Construction

Start Date: April 2019
Projected Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $1,947,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 06/17/2019