Bridge Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    40% complete

This project will reconstruct Bridge Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: January 2020
Completion Date: January 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $2,575,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Bridge Playground , Bronx
Boscobel Place, Undercliff Avenue, University Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 07/26/2021