NYCHA Pomonok Houses Open Space Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    59% complete

This project will construct a new open space within the NYCHA Pomonok Houses.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: April 2021

Construction

Start Date: June 2021
Projected Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $3,000,000
Funding Source: Mayoral

Location

71st Avenue between Kissena Boulevard and Parsons Boulevard

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 05/25/2022