Grant Park Construction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct Grant Park, including converting the roadbed to recreational space.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: May 2019
Projected Completion Date: November 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Borough President

Location

Grant Park , Bronx
Grant Avenue between East 169th Street and East 170th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/19/2020