Queens Tree-Damaged Sidewalk Reconstruction FY19 - Community Boards 8,11-14

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Queens Community Boards 8 and 11-14.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2018
Projected Completion Date: May 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: August 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $2,202,000
Funding Source: Mayoral

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project