Randall's Island PEP Academy Complex Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the parking lot at the Randall's Island Parks Enforcement Patrol (PEP) Academy Complex.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: March 2018
Projected Completion Date: July 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Private

Location

Randall's Island Park , Manhattan
Hell Gate Circle between Sunken Meadow Loop and Rivers Edge Road, under the Robert F. Kennedy Triborough Bridge

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 12/15/2018