Randall's Island PEP Academy Complex Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will reconstruct the parking lot at the Randall's Island Parks Enforcement Patrol (PEP) Academy Complex.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2018
Projected Completion Date: July 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: April 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $4,703,000
Funding Source: Mayoral

Location

Randall's Island Park , Manhattan
Hell Gate Circle between Sunken Meadow Loop and Rivers Edge Road, under the Robert F. Kennedy Triborough Bridge

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 05/29/2020