Morton Playground Reconstruction
-
100% complete
-
100% complete
-
95% complete
This project will reconstruct Morton Playground, including the basketball courts, play equipment, safety surface, water and drainage systems, park lighting, and landscaping.
Project Update: This project is in active construction.
Project Timeline
Design
Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date:
September 2019
Procurement
Start Date: September 2019
Projected Completion Date:
June 2020
Completion
Date:
April 2021
Construction
Start Date: July 2021
Projected Completion Date:
July 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Aqueduct Walk
, Bronx
University Avenue and Morton Place
Project Staff
Project Liaison: Mike Ortiz
Contact NYC Parks
about this project