Ridgewood Reservoir Invasive Species Removal
-
100% complete
-
60% complete
-
0% complete
This project will remove invasive species and plant new and replacement trees at Ridgewood Reservoir in Highland Park.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: March 2018
Projected Completion Date:
December 2018
Completion Date:
May 2019
Procurement
Start Date: May 2019
Projected Completion Date:
February 2020
Adjusted Completion
Date:
June 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Highland Park
, Queens
Vermont Place, Highland Boulevard, Jackie Robinson Parkway, Cypress Hills Street
Project Staff
Contact NYC Parks about this projectLast updated: 05/27/2022