Manhattan Beach Center Promenade Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    38% complete

This project will reconstruct the center portion of Manhattan Beach Promenade, around the bathhouse and entryways to the beach with new concrete pavement, drainage, seating, landscaping, steps, and ADA-compliant ramps.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020
Completion Date: June 2021

Construction

Start Date: June 2021
Projected Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $453,000
Funding Sources:
  • Mayoral
  • Federal

Location

Manhattan Beach Park , Brooklyn
Oriental Boulevard between Ocean Avenue and Mackenzie Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/19/2021