Highland Park Ridgewood Reservoir Gatehouse 27 Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct Gatehouse 27 next to Ridgewood Reservoir in Highland Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: December 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Highland Park , Queens
Jackie Robinson Parkway between Vermont Place and Cypress Hills Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 10/19/2021

Was this information helpful?