Orchard Beach Nature Center Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Orchard Beach Nature Center in Pelham Bay Park.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: August 2018
Projected Completion Date: May 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Pelham Bay Park , Bronx
North section of Orchard Beach Boardwalk

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 09/25/2018