Queens Tree-Damaged Sidewalk Reconstruction FY19 - Community Boards 1-7,9,10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    62% complete

This project will reconstruct sidewalks damaged by adjacent city-owned trees in Queens Community Boards 1-7, 9, and 10.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2018
Projected Completion Date: May 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: July 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $3,156,000
Funding Sources:
  • Mayoral
  • City Council

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020