Alley Pond Park Living Shoreline Construction Phase 1

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a living shoreline with oyster habitats along the western shore of Alley Creek at Alley Pond Park.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: October 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: June 2020
Completion Date: November 2020

Construction

Start Date: February 2021
Projected Completion Date: August 2021
Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $91,000
Funding Source: Federal

Location

Alley Pond Park , Queens
Western shoreline of Alley Creek near Cross Island Parkway and Northern Boulevard

 

Project Staff

Contact NYC Parks about this project

Last updated: 08/17/2022

Was this information helpful?