Alley Pond Park Living Shoreline Construction Phase 1

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a living shoreline with oyster habitats along the western shore of Alley Creek at Alley Pond Park.

Project Update: The schematic design for this project has been approved. Parks is now developing construction documents for this project and applying for necessary permits.

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: October 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Federal

Location

Alley Pond Park , Queens
Western shoreline of Alley Creek near Cross Island Parkway and Northern Boulevard

 

Project Staff

Contact NYC Parks about this project

Last updated: 10/18/2018