Grove Hill Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will reconstruct the comfort station in Grove Hill Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: January 2019
Completion Date: January 2019

Procurement

Start Date: January 2019
Projected Completion Date: October 2019
Completion Date: March 2020

Construction

Start Date: October 2020
Projected Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $1,551,000
Funding Source: Mayoral

Location

Grove Hill Playground , Bronx
East 158th Street between Eagle Avenue and Cauldwell Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/19/2020