White Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the playground in White Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020
Adjusted Completion Date: October 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: State

Location

White Park , Staten Island
Lyman Avenue between High Street and Bay Street

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 08/07/2020