St. Mary's Park Ballfields and Dog Run Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the ballfields and dog run, including natural turf, irrigation, sports lighting, fencing and landscaping at St. Mary's Park.
Project Timeline
Design
Start Date: November 2016
Projected Completion Date:
December 2017
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
September 2018
Completion
Date:
November 2018
Construction
Start Date: December 2018
Projected Completion Date:
March 2020
Completion
Date:
June 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
St. Mary's Park
, Bronx
St. Mary's Street and Jackson Avenue
Project Staff
Project Liaison: Mike Ortiz
Contact NYC Parks
about this project
Last updated: 05/18/2022