St. Mary's Park Ballfields and Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the ballfields and dog run, including natural turf, irrigation, sports lighting, fencing and landscaping at St. Mary's Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

St. Mary's Park , Bronx
St. Mary's Street and Jackson Avenue in St. Mary's Park

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 05/21/2018