St. Mary's Park Ballfields and Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    77% complete

This project will reconstruct the ballfields and dog run, including natural turf, irrigation, sports lighting, fencing and landscaping at St. Mary's Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: November 2018

Construction

Start Date: December 2018
Projected Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $8,922,000
Funding Source: Mayoral

Location

St. Mary's Park , Bronx
St. Mary's Street and Jackson Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/13/2019